Question no 3359 : Setting up QM for UD only

In SAP QM as at ECC6.0 EhP7, to setup QM for UD only (without RR), the mandatory requirements are the following ?

(more than one answer)

A)   Activate an Inspection Type in the Material Master QM data view.
B)   Assign a Sampling Technique in the Inspection Type detail.
C)   Minimum of One Master Inspection Characteristics.
D)   A Material Specification with only one Master Inspection Characteristics.
E)   Check Auto UD in the Inspection Type detail.
.

1 comment:

  1. Answer: A, B

    MIC, Material Spec, Inspection Plan are not required. Auto UD has no concern on the question, so it can be with or without.