Question no 3332 : Routing and BOM creation in PP

In SAP PP as at ECC6.0 EhP6, which of the following creation scenarios are correct for PP BOM and Routing ?

(more than one answers)

A)   CS01 can save a BOM without a Plant.
B)   CS01 can save a BOM without a Material.
C)   CA01 can save a Routing without a Plant.
D)   CA01 can save a Routing without a Material.
E)   CA01 can save a Routing without a Plant and without a Material.
.

1 comment:

  1. Answer: A, D

    CS01 initial screen must have Material, BOM usage, and Key Date
    CA01 initial screen must have Plant and Key Date.