Question no 3317 : ERS scenario

In SAP MM as at ECC6.0 EhP6, which of the following scenario must use the ERS vendor ?

(more than one answers)

A)  Consignment.
B)  Subcontracting.
C)  Pipeline.
D)  Invoicing Plan.
E)  Consumables.
.

1 comment:

  1. Answer: A, C, D

    MRRL for PO with ERS (but its dependent on process requirements)
    MRKO for consignment and pipeline settlement (mandatory ERS for this process)
    MRIS for invoicing plan settlement (mandatory ERS for this process)