Question no 3275 : Move time

In SAP PP as at ECC6.0 EhP6, which of the following in the work center master is used in the move time matrix to define the move times between work centers ?

(only one answer)

A)  Location.
B)  Storage Location.
C)  Location Group.
D)  Functional Location.
E)  Plant Section.
.

1 comment:

  1. Answer: C

    The Location Group assigned to each Work Center.