Question no 3265 : Maintenance Notification System status

In SAP PM as at ECC6.0 EhP6, when all tasks in the Maintenance Notification are completed, which of the following system status is set at the Maintrnance Notification header ?

(only one answer)

A)  NOCO
B)  TSCO
C)  ATCO
D)  ATTSCO
E)  COTS
.