This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Wednesday, September 14, 2016

Question no 3253 : Inspection Lot creation

In SAP QM as at ECC6.0 EhP6.0, for an Inspection Lot to be created as a Release Status successfully, which of thr following are mandatory ?

A)  Activation of an Inspection Type in thr Material Master. 
B)  A valid Sampling Procedure. 
C)  An Inspection Plan or Material Specification. 
D)  A QM Control key in thr Material Master QM data view. 
E)  Avalid Quality level.
.

2 comments:

  1. B) Sampling Procedure is mandatory for calculation of the sample size in thr Inspection lot for it to be released.
    C) Both Inspection Plan nor Material Specification is not necessary, and without them; Results Recoding is not required.
    D) QM control key is for MM for QM and even then it is not mandatory.
    E) Quality level is available when Dynamic Modification was activated for thr Material Inspection but it is not a mandatory feature.

    ReplyDelete

These questions are not moderated and solely created by the blogger; However, I have tried my best to provide correct answers and some explanations. Please feel free to drop me a mail only when you need clarification and provided you have thoroughly checked your understanding of the question.

Note: Only a member of this blog may post a comment.