Question no 3229 : Planned Independent Requirement item schedule

In SAP PP as at ECC6.0 EhP6, which of the following can be assigned to a Planned Independent Requirement item schedule ?

(more than one answers)

A)  BOM explosion number.
B)  BOM usage.
C)  Production version.
D)  Product group.
E)  Scrap factor.
.

2 comments:

  1. Each Qty with a period can be assigned to BOM explosion number or Production version, check this out either in MD61 or MD62.