This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Thursday, August 4, 2016

Question no 3227 : MRP Area in the Material Master

In SAP PP MRP Area as at ECC6.0 EhP6, which of the following data fields are mandatory at the MRP Area level parameter in the Material Master ?

(more than one answers)

A)   MRP Group.
B)   MRP Controller.
C)   MRP Type.
D)   Special Procurement Key.
E)   Planned Delivery Time.
.

2 comments:

These questions are not moderated and solely created by the blogger; However, I have tried my best to provide correct answers and some explanations. Please feel free to drop me a mail only when you need clarification and provided you have thoroughly checked your understanding of the question.