Question no 3216 : MRP run Delay Analysis

In SAP PP MRP as at ECC6.0 EhP7, which of the following Planning options allow you to view the Delays of Planned Orders in a Multi-level BOM and resolve its delay in the Planning Results ?

(only one answer)

A)  MD02 Multilevel Single-Item Planning in Simulation Mode.
B)  MD03 Single-Level Single-Item Planning in Simulation Mode.
C)  MD43 Single-Item Planning, Interactive Mode.
D)  MS43 Long Term Planning, Interactive Mode.
E)  MDBT Total Planning in Simulation Mode.
.

2 comments:


  1. MD02, MD41, MS02 all have Simulation Modes that extrapolate the Delays for analysis and resolution in the Planning Results.
    MD02 is in the MRP folder
    MD41 is in the MPS folder
    MS02 is in the LTP folder

    ReplyDelete