Question no 3211 : Scenario parameters for LTP in PP

In SAP PP as at ECC6.0 EhP7, which of the following are parameters which you can setup in the Planning Scenario for LTP (Long Term Planning) ?

(more than one answers)

A)  Choice of Plants to the Scenario.
B)  Switch off Make-to-Order features.
C)  Use a different Routing.
D)  Use a different Lot Size Key.
E)  Inclusion of Firm Planned Orders.
.


2 comments:

  1. You cannot choose a different Routing but you can setup a choice of Capacity Version (of the Capacity Header)