This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Wednesday, June 29, 2016

Question no 3196 : MM Plant level Master data

In SAP MM as at ECC6.0 EhP7, which of the following need not be created at the Plant level ?

(more than one answers)

A)   Source List.
B)   Quota Arrangement.
C)   Purchasing Info Record.
D)   Contract.
E)   Scheduling Agreement.
.

3 comments:

  1. C) An option to create the PIR with or without Plant, and this is in accordance to Purchasing Negotiation strategy (PIR without Plant means an ability to negotiate one price for all plants by a Purchasing Organization)

    ReplyDelete
  2. D) Central Contract without Plant usually negotiates a Total quantity with a base price for several plants, subsequently purchase orders called "Released Orders" will be created with reference to the Contract for each Plant.

    ReplyDelete

These questions are not moderated and solely created by the blogger; However, I have tried my best to provide correct answers and some explanations. Please feel free to drop me a mail only when you need clarification and provided you have thoroughly checked your understanding of the question.

Note: Only a member of this blog may post a comment.